Latest Project Update
Site preparation and foundation are complete. Structure and roof activities are underway across the Golden Gate Phase 1 townhouse and guesthouse buildings (~35% complete).
Recent Progress
- Site preparation complete
- Foundation complete
- Structure and roof package in progress
Next Steps
- Complete structure and roof dry-in
- Begin interior framing, doors, and wall systems
- Continue weekly field reporting to ownership